Construction at Coralinus 1 site is getting fast and furious.Construction for the Multi Storey Carpark has been ongoing for some time and it’s currently at Level 3.

As for the remaining blocks, here are the updates;
Blk 301A – Level 11 completed
Blk 301B – Level 12 completed, going on Level 13
Blk 301C – Level 11 completed
Blk 303A – Level 4
Blk 303B – Level 7
Blk 303C – Currently building Level 8