Coralinus and Sundial updates

Sundial

Construction at Coralinus 1 is progressing well, while foundation works is still going on at Coralinus 2. For Sundial, its near completion and painting works has commenced for Blk 167A. Construction workers are doing finishing touches to the other blocks.

For Coralinus 1, the detailed update as follows;
MSCP – Level 3 completed, currently Level 4 in progress
Blk 301A – Level 13 completed, currently Level 14 in progress
Blk 301B – Level 13 completed, currently Level 14 in progress
Blk 301C – Level 13 completed, currently Level 14 in progress
Blk 303A – Level 4 completed, currently Level 5 in progress
Blk 303B – Level 9 completed, currently Level 10 in progress
Blk 303C – Level 8 completed, currently Level 9 in progress